Thursday, October 29, 2009
16 October 2009
Holes were drilled to give way for the piers. A total of 57 holes were drilled with depth ranging from 0.8 meter to 1.7 meters with total depth of 72.9 linear meters. I forgot to bring my camera, sorry no pic this time.
02 October 2009
Hi everyone, it took me more than a month to get back to this blog. It looks like I'm losing my momentum. Anyway, I'm back to give you a delayed update on the development of my home project with AV Jennings. After the 18 Sept cut-and-fill job, there was a zero activity on site for the next two weeks. The drainers/plumbers came on the 2nd of Oct to layout the subfloor drains, conduits, etc.