Thursday, October 29, 2009

21 October 2009










Formworks for the perimeter of the slab area were layed and the slab area was screeded level.

16 October 2009

Holes were drilled to give way for the piers. A total of 57 holes were drilled with depth ranging from 0.8 meter to 1.7 meters with total depth of 72.9 linear meters. I forgot to bring my camera, sorry no pic this time.

02 October 2009


Hi everyone, it took me more than a month to get back to this blog. It looks like I'm losing my momentum. Anyway, I'm back to give you a delayed update on the development of my home project with AV Jennings. After the 18 Sept cut-and-fill job, there was a zero activity on site for the next two weeks. The drainers/plumbers came on the 2nd of Oct to layout the subfloor drains, conduits, etc.